Critical Path Method (CPM) Calculator

Forward pass · Backward pass · Total & free float

Reviewed November 2026 · Civil Systems LLC

See which activities control the finish date, and how far everything else can slip before it does.

Pick an example network or build your own with up to six activities. Change a duration and every early date, late date, and float value recalculates on the spot. Then switch modes to practice on the same network: find the critical path, fill in the blanks like an exam, or predict what a change will do.

01 / Explore and practice

One network, four ways to work it

ES
Early start
EF
Early finish
FF
Free float
LS
Late start
LF
Late finish
TF
Total float
  • Critical path
  • Selected activity

Activity inspector

Activity A

Select a box in the network to edit that activity.

Predecessors

Select every activity that must finish before this one starts.

Full schedule table
Calculated schedule · elapsed time units from 0
ActivityESEFLSLFTFFFStatus
02 / Understand

Total float vs. free float

Both measure slack, but they protect different things. Free float protects the next activity and belongs to one activity. Total float protects the project finish and is shared along a path until it merges with another.

Free float (FF)

How long an activity can slip before any successor has to start later.

FF = min(successor ES) − EF

Total float (TF)

How long an activity can slip before the project finish moves.

TF = LS − ES = LF − EF

Watch the float run out

In the “Float at a merge” network, B sits beside the longer A–C chain. Stretch B one unit at a time:

  1. B = 3 3 units of free float, 4 units of total float. Nothing downstream notices a small slip.
  2. B = 6 Free float is gone. Any more delay pushes E later.
  3. B = 7 E now starts later and total float is gone. B is critical.
  4. B = 8 The project finish moves from 11 to 12.

A terminal activity uses the project finish in place of a successor. A network can have more than one critical path.

03 / Work it through

Step-by-step solution

The three steps you would write out on an exam: forward pass, backward pass, then float. Every substitution is shown for the network above.

Common questions
What is the forward pass in CPM?

The forward pass moves through the network from start to finish and finds each activity’s earliest start (ES) and earliest finish (EF). An activity’s ES is the largest EF among its predecessors, because it cannot start until all of them are done. Then EF = ES + duration. The largest EF in the network is the earliest possible project finish.

What is the backward pass in CPM?

The backward pass starts at the project finish and works back to the start, finding each activity’s latest finish (LF) and latest start (LS). An activity’s LF is the smallest LS among its successors. Then LS = LF − duration. Terminal activities take the project finish as their LF. In a hand calculation that finish is the early finish from the forward pass; scheduling software can also start the backward pass from an imposed finish date.

What is the difference between total float and free float?

Total float is how long an activity can slip before the project finish moves: TF = LS − ES. Free float is how long it can slip before any successor’s earliest start moves: FF = smallest successor ES − EF. Free float is never larger than total float. Free float belongs to one activity. Total float is shared by every activity along a path up to the point where it merges with another path, so when one activity uses some of it, the activities after it have that much less.

How do you find the critical path?

The critical path is the longest path through the network, so it sets the shortest possible project duration. Run the forward and backward pass, then calculate total float: in a network without imposed dates, the activities on the critical path have zero total float. Follow the links between them from start to finish. More than one path can tie for longest, and a near-critical path with a unit or two of float deserves nearly as much attention. PMI calls these critical path activities and uses critical activities more broadly, for any high-risk work the project depends on, on the critical path or not.

Why does my textbook start activities on day 1 instead of 0?

Some courses count calendar days, so the first activity starts on day 1 and EF = ES + duration − 1. This calculator counts elapsed time from 0, so EF = ES + duration. The two conventions shift the start dates by one but give the same project duration, the same float, and the same critical path. Use whichever your course or exam expects.

Does this calculator handle lags or start-to-start links?

No. It models finish-to-start links with zero lag, which is the standard setup for learning the forward and backward pass. Lags, start-to-start and finish-to-finish links, work calendars, resource limits, and imposed dates need full scheduling software.

Model assumptions. Activity-on-node network (the precedence diagramming method used by modern scheduling tools), finish-to-start links, zero lag, whole-number durations from 0 to 999, no resource limits or imposed dates. Time starts at 0 and values are elapsed units, not calendar dates. Zero-duration activities (milestones) are allowed. Built for learning and for checking hand calculations. Terms and definitions follow PMI’s Practice Standard for Scheduling, Third Edition (sections 2.2.1, 3.4.1, and 3.4.2).